NLTP - National Land Transport Programme

Regional and nationwide programmes | June 2008

Nationally delivered programmes

« Return to NLTP 2008 table of contents

This section presents the key aspects of the NLTP for nationally delivered programmes. It sets out the key statistic of transport in the region and presents tables of the new National Land Transport Programme (NLTP) appropriate to the region.

Phase Profile Status Expected start year Work category FAR
Total phase cost ($000)
Total cost 2008/09 ($000)
2008/09 NLTA ($000)
Indicative funding source
Land Transport NZ            
Maintenance and operation of local roads            
Emergency works            
Unallocated            
-
-
51,132.9
N
Renewal of local roads            
Preventive maintenance            
Unallocated            
-
-
4,845.0
N
Improvement of local roads            
New road infrastructure            
Unallocated            
-
-
36,512.6
N
Unallocated            
-
-
59,526.5
R/C
Use of the land transport system            
Studies            
Unallocated            
-
-
3,034.0
N
Walking and cycling            
Unallocated            
-
-
4,450.1
N
Unallocated            
-
-
2,357.3
R/C
Rail freight and sea freight            
Unallocated            
-
-
824.0
N
Seed funding for Coastal Shipping            
Unallocated            
-
-
6,000.0
N
Community focused activities            
Unallocated            
-
-
2,921.1
N
Passenger transport            
New passenger transport infrastructure            
Unallocated            
-
-
29,585.1
N
Unallocated            
-
-
5,526.5
R/C
Services and operations            
Unallocated            
-
-
11,259.0
N
Administration            
Territorial            
Unallocated            
4,332.7
N
Research, education and training            
Research, education and training            
27,597.0
N
Transit - National            
Maintenance and operation of state highways            
Routine maintenance     App 2008/09   100
12,511.7
12,511.7
12,511.7
N
Property            
Block allocation            
14,000.0
N
Emergency works            
Unallocated            
18,775.0
18,775.0
18,775.0
N
Renewal of state highways            
Periodic maintenance     App 2008/09   100
50.0
50.0
50.0
N
Preventive maintenance            
Unallocated            
4,000.0
4,000.0
4,000.0
N
Improvement of state highways            
New road infrastructure            
Toll Systems Project D   Com 2005/06 321 100
7,282.3
785.0
785.0
N
Toll Systems Project - Stage 1 C   Com 2007/08 321 100
21,814.0
6,544.0
6,544.0
N
Unallocated            
-
-
22,922.9
N
Unallocated            
36,258.2
R/C
Investigations from Strategic Studies            
Block allocation     App      
4,000.0
N
Strategic Studies            
Block allocation     App      
9,000.0
N
Improved Driver Information            
Block allocation     App      
5,000.0
N
Improvements Maintenance LOS            
Block allocation     App      
3,000.0
N
Strategic Plan Initiatives            
Block allocation     App      
14,000.0
N
Property Purchase            
Block allocation     App      
70,898.4
N
Block allocation     App      
25,101.6
R
Small and Medium sized projects            
Block allocation     App      
74,907.8
N
Block allocation     App      
18,092.2
R
Use of the land transport system            
Walking and cycling            
Block allocation     App 2008/09    
5,000.0
5,000.0
5,000.0
Community focused activities            
Advertising programme I MMM App   433 100
500.0
500.0
500.0
N
Administration            
State highways            
State highway administration     App 2008/09   100
57,800.0
57,800.0
57,800.0
N

Return to NLTP 2008 table of contents